Installation
Norbord structural panels are to be installed according to the APA’s (The Engineered Wood Association) Construction Guide E30 and the appropriate building code. Below are some key installation points.
 
  1. Allow a minimum of 1/8” spacing on the 4’ edges.
  2. Make sure joist alignment is uniform and square.
  3. Install panels with the major strength axis perpendicular to supports.
  4. Lightly butt the T&G together.
  5. Install T&G panels with the APA grade stamp down.
  6. Fastener spacing*
  7. Gluing sub-floor panels is always recommended and may be required. We recommend the use of PL 400 subfloor adhesive. At a minimum, sub-floor adhesives must meet current industry test standards. If glue is used, apply only enough glue to install 2 or 3 panels at a time and fully fasten the panels before continuing.
  8. Building codes require an impermeable moisture barrier on top of the ground cover in all crawl spaces.
*Consult your local building codes for local requirements and specifications and the APA Construction Guide E30.
 

The following floor coverings may be installed over Pinnacle:

Always follow the floor covering/installation product manufacturers’ application recommendations.

  • Commercial and residential carpet and under pad.
  • Ceramic Tile and lightweight concrete.
  • Hardwood floors, (Solvent based adhesives are recommended when gluing parquet hardwood flooring).
  • Vinyl flooring requires a suitable underlayment.
Click here to access the APA website
 
Click here to access the new Pinnacle Product website
 
Click here to view the Pinnacle Brochure (PDF - 959KB)
 
Click here for the OSB Information Sheet (PDF - 114KB)
 







Pinnacle from Norbord is a certified "Green Approved Product" for the National Green Building Standard
Terms and Conditions | Privacy | Forward-Looking Statements